PMP考试每天一练-2018年PMP考试试题162
PMP考试试题一: A project requires internal resources and external resources. External resources are acquired through a standard procurement plan. After a hurricane strikes the contracted supplier’s location, they can no longer meet the required timeline for the deliverables Which contractual component will clarify the financial resolution of the supplier’s failure to meet contracted terms? A.Force majeure clause B.Incentive clause C.Reimbursement clause D.Arbitration clause 一个项目需要内部资源和外部资源。外部资源通过一份标准采购计划获得。在一场飓风袭击分包供应商所在地后,他们无法满足可交付成功要求的时间限制。哪一个合同部分将澄清供应商未能满足该合同条款的财务解决方式? A.不可抗力条款 B.激励条款 C.补偿条款 D.仲裁条款 PMP答案解析:飓风是不可抗力因素 PMP参考答案:A PMP考试试题二 Project team members feel empowered to work independently and believe that the project manager trusts them to deliver their tasks without managing the team too closely.Which management style does the project manager demonstrate? A.Need for affiliation B.Theory x C.Theory y D.Need for power 项目团队成员认为能够独立工作,并认为项目经理信任他们能在不严密管理团队的情况下交付任务。项目经理证明的是哪一种管理方式? A归属需求 B.X理论 C.Y理论 D.权力需求 PMP答案解析:人之初,性本勤 PMP参考答案:C |