PMP考试试题一:

A project manager receives an approved project scope based on a cost estimate and begins the implementation of a new software system, What type of cost estimate was used at implementation'?

A. Parametric

B. Bottom-up

C. Rough order of magnitude (ROM)

D. Analogous

项目经理收到基于成本估算的已批准项目范围,并开始实施新的软件系统。实施时使用的是什么类型的成本估算?

A.参数估算

B.自下而土估算

C.粗略量级估算(ROM)

D.类比估算

PMP答案解析:已批准的范围,可以理解为范围基准清楚、基于WBS的估算为自下而上估算。本题中没有看到和参数估算有关的数据与统计类数值,同时也没有体现出粗略量级估算相关的的信息(-25%,+75%),排除C

PMP参考答案:B

PMP考试试题二

A project manager works with the sales manager on a request for proposal(RFP). The customer is interested in a new product feature which is still under development. The sales manager asks the project manager to include in the response that the feature is available.What should the project manager do?

A.Respond according to the sales manager’s suggestion

B.Escalate the issue to the project sponsor

C.Advise the customer that the product feature is not available

D.Refuse to respond to the RFP

项目经理与销售经理一起合作答复建议邀请书(FRP)。客户对一个仍处于开发阶段的新产品功能非常感兴趣。销售经理要求项目经理在答复中包含可提供该功能的内容项目经理应该怎么做?

A.按照销售经理的建议答复

B.将该问题上报给项目发起人

C.通知客户无法提供该产品功能

D.拒绝答复该RFP

PMP答案解析:比较稳当的做法是上报发起人,咨询他的意见。新产品还在开发,如果在建议邀请书中就列出来风险太高。排除 A C和 D太绝对了,不积极主动

PMP参考答案:B

阅读本文的人还阅读了:
PMP的价值在哪?
PMP认证考试的报名条件?
PMP是什么?
pmp考试时间是哪天?
如何挑选pmp培训班?
pmp认证培训费用多少?
pmp项目管理师是什么?
pmp证书是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库