PMP考试每天一练-2018年PMP考试试题137
PMP考试试题一: A project manager identifies a risk on a project which causes work to stop. The project team was forced to use a contingency plan In what project management process group is the project manager currently in? A.Control risk B.Plan risk responses C.Identify risks D.Mitigate risks 项目经理识别到项目上的一个风险可能导致停工。项目团队被迫使用应急计划项目经理目前处于那一个项目管理过程组? A.控制风险 B.规划风险应对 C.识别风险 D.减轻风险 PMP答案解析:实施应对计划是控制风险过程 PMP参考答案:A PMP考试试题二 During the planning phase, the project team gathers requirements from the client on multiple occasions with multiple team members. Which of the following group creativity techniques would assist the project team and the client to generate and collect multiple ideas related to the requirements? A.Observations B.Questionnaires and surveys C.Prototypes D.brainstorming 在项目规划阶段,项目团队采用多名团队成员在多种场合收集客户的需求。下列哪一项群体创新技术将帮助项目团队和客户产生的收集与需求有关的多种创意? A.观察 B.问卷调查 C.原型法 D.头脑风暴法 PMP答案解析:四个选项都是收集需求的工具,题目问的是收集需求的群体创新技术,头脑风暴 PMP参考答案:D |