PMP考试试题一: During project initiation, the project manager learns that the format project contract is not signed. What should the project manager do next? A.Discuss with the project sponsor B.Stop the project C.Consult with the stakeholders D.Discuss with senior management 在项目启动阶段,项目经理了解到还未签署正式合同项目。项目经理接下来应该怎么做? A.与项目发起人协商 B.停止项目 C.咨询项目关系人 D.与高级管理层协商 PMP答案解析:发起人解决超出PM权限范围外的事 PMP参考答案:A PMP考试试题二 Halfway through a software project, the customer wants to add additional feature, but with no additional cost. What should the project manager do? A.Discuss the request with the customer to understand the impact B.Escalate the request to senior management to seek advice C.Agree to add the feature to improve customer satisfaction and demonstrate flexibility D.Reject the request as this is not a part of the agreed scope of work 在一个软件项目的中途,客户希望添加一项额外功能,但不增加成本。项目经理应该怎么做? A.与客户讨论该请求,了解对项目的影响 B.将该请求上报给高级管理层,寻求建议 C.同意添加功能,提高客户满意度并验证可行性 D.拒绝请求,因为这不属于约定工作范围的组成部分 PMP答案解析:直接同意和直接拒绝都是不对的,排除C和D。应该与客户先讨论增加额外功能的影响 PMP参考答案:A |