以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2018年PMP考试试题117

转载者:PMP团购网      发布时间:2018/9/28        点击: 2349

PMP考试试题一:

While estimating an activity cost, the team members estimate US$5,000 to hire a consultant for the next year, divided as follows:

US$4,500 - Consultant fee

US$200 – Inflation allowance for next year

US$300 – Buffer for unforeseen costs

What should the project manager do next?

A.Estimate US$4,700

B.Estimate US$5,000 with an explanation

C.Estimate US$5,000 and update the cost baseline

D.Estimate US$4,800

估算一项活动成本时,团队成员估算下一年要花费5000美元聘用一名顾问,划分如下

4500美元-顾问费

200美元-下一年的通货膨胀余量

300美元-不可预见成本的缓冲

项目经理接下来应该怎么做?

A.估算4700美元

B.估算5000美元,并附加说明

C.估算5000美元,并更新成本基准

D.估算4800美元

PMP答案解析:4500活动成本,200应急储备,300管理储备。为应对成本的不确定性,成本估算中可以包括应急储备

PMP参考答案:A

PMP考试试题二

During project execution, the company is sold and the stakeholders change. A new stakeholder asks how the project aligns with the company’s business needs.Which document should the project manager review with the stakeholder?

A.Project management plan

B.Stakeholder management plan

C.Project charter

D.Requirements documents

在项目执行期间,公司被出售,干系人发生变化。一名干系人询问项目如何与公司的业务需求保持一致。项目经理和该干系人将审查下列那一份文件?

A.项目管理计划

B.干系人管理计划

C.项目章程

D.需求文档

PMP答案解析:章程中有项目的目的、目标、以及被审批的原因

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
保定PMP考试地点在哪里?
杭州PMP考试地点在哪里?
苏州PMP考试地点在哪里?
无锡PMP考试地点在哪里?
常州PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库