PMP考试每天一练-2018年PMP考试试题116
PMP考试试题一: A project manager is working on a project’s quality management plan. The project manager should consider which of the following when determining the project’s cost of quality(COQ)? A.Training, inspections, rewards, and lost business B.Rewards, inspections, rework, and lost business C.Training, rewards, rework, and lost business D.Training, inspections, rework, and lost business 项目经理正在制定项目的质量管理计划。在确定项目的质量成本(COQ)时,项目经理应考虑下列哪一项? A.培训、检查、奖励和业务流失 B.奖励、检查、返工和业务流失 C.培训、奖励、返工和业务流失 D.培训、检查、返工和业务流失 PMP答案解析:考虑一致性成本与非一致性成本 PMP参考答案:D PMP考试试题二 During project execution, two teams prove inefficient with systems integration, which causes scheduling issues. What should the project manager do? A.Use collaborative tools. B.Update the issue log. C.Define clear rules. D.Meet with the team supervisor. 项目执行过程中,团队在系统集成工作中效率低下,已经造成进度问题,项目经理需要如何处理? A.应用协同工具。 B.更新问题日志。 C.制定明确的规则。 D.与团队主管开会。 PMP答案解析:C参考答案可以理解为建设项目团队中的“基本规则”这个工具,制定基本规则有利于减少误解,提高生产力 PMP参考答案:C |