PMP考试试题一:

During a project, the project manager is informed of new requirements that need to be delivered. The project manager also learns that two resources will be removed from the project, which will impact the schedule.To evaluate the impact of these changes and risks to the project’s execution, what should the project manager reference?

A.Project management plan

B.Work breakdown structure

C.Resource schedule

D.Change management plan

在项目期间,项目经理收到交付新需求的通知。项目经理还了解到两名资源将从项目离开,从而影响了进度。为了评价这些变更和风险对项目执行的影响,项目经理应查阅那一份文件?

A.项目管理计划

B.工作分解结构

C.资源进度计划

D.变更管理计划

PMP答案解析:变更和风险,综合来看需要查阅项目管理计划

PMP参考答案:A

PMP考试试题二

A project with an estimated cost of US$5 million is approved and funded. The project manager is entitled to a 1% bonus on any cost savings if the project finishes under US$5 million. At the completion of the project, the actual cost savings and the bonus amount paid should be documented and archived.This information could be used in future projects for which of the following purposes?

A.Estimating the budget

B.Determining the project manager’s future compensation

C.Assisting in future vendor selections

D.Adding to the lessons learned document repository

估算成本为500万美元的项目已获批准且资金到位。如果项目在500万美元以内完成,项目经理将根据节省的任何成本,有权获得1%的奖金。在项目完成时,应记录并存档节省的实际成本和支持的资金金额、该信息可以出于下列哪一种目的在未来项目中使用?

A.估算预算

B.确定项目经理的未来补偿

C.帮助未来的供应商选择

D.添加到经验教训文档库中

PMP答案解析:将这些信息添加到经验教训文档中,供未来项目参考

PMP参考答案:D

阅读本文的人还阅读了:
PMP考试有什么科目?
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
北京PMP考试地点在哪里?
上海PMP考试地点在哪里?
PMP认证报名条件是什么?
不参加PMP培训可以考PMP吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库