PMP考试每天一练-2018年PMP考试试题112
PMP考试试题一: During a project’s execution in a weak matrix organization, the functional manager, project sponsor, and project manager discuss how to improve a team member’s knowledge and skills. Who is responsible to address these needs? A.Functional manager B.Human resource department C.Project manager D.Project sponsor 在一个弱矩阵式组织中的项目执行期间,职能经理、项目发起人和项目经理讨论如何提高团队成员的知识和技能。谁应该负责解决这些需求? A.职能经理 B.人力资源部门 C.项目经理 D.项目发起人 PMP答案解析:弱矩阵环境中,职能经理的权力大于项目经理 PMP参考答案:A PMP考试试题二 Which of the following is the final task in a project? A. Completing a lessons learned review and update B. Transporting the accepted deliverables to the client C. Archiving the project records D. Disbanding the project team 下列哪一项属于一个项目的最终任务? A. 完成经验教训审查和更新 B. 将已验收的可交付成果运送给客户 C. 项目记录存档 D. 解散项目团队 PMP答案解析:收尾的最后一步,资源解散 PMP参考答案:D |