PMP考试每天一练-2018年PMP考试试题108
PMP考试试题一: A change request for additional features was approved at the last project steering committee meeting. What should the project manager do next? A.Direct the development team to continue with the current project management plan B.Update the project management plan and other necessary project documentation C.Meet with the development team to discuss the change request D.Direct the development team to complete the additional features 在最近一次项目指导委员会会议上,额外功能的变更请求获得批准。项目经理接下来应该怎么做? A.指示开发团队继续当前的项目管理计划 B.更新项目管理计划和其他必要的项目文档 C.与开发团队开会,讨论变更请求 D.指示开发团队完成额外功能 PMP答案解析:变更请求获得批准后,下一步是更新项目管理计划/项目文件 PMP参考答案:B PMP考试试题二 During project implementation, a stakeholder indicates that some deliverables do not comply with specifications. The project manager states these specifications were discussed in project meetings, and the agreed outcomes were communicated and documented in published reports.To avoid this outcome, what should have been done in the planning phase? A.Analyzed communication requirements in the stakeholder management plan B.Included the stakeholders in the quality management plan preparation C.No action is necessary, the stakeholder should have reviewed the distributed information D.Addressed deliverables and expectations at the kick-off meeting 在项目实施期间,一名干系人指出某些可交付成果不符合规范要求。项目经理表示规范要求已在项目会议上讨论过,并已沟通了约定成果,记录在发布的报告中。为避免这种情况,在规划阶段应完成那一项工作? A.在干系人管理计划中分析沟通需求 B.将干系人包含在质量管理计划准备过程中 C.没有必要采取任何行动, 干系人应以查看分发的所有信息 D.在项目启动大会上公布可交付成果和期望 PMP答案解析:干系人指出可交付成果不符合规范要求,说明是质量不达标。那么应该做好质量管理,尽早让干系人参与到质量管理计划中 PMP参考答案:B |