PMP考试试题一:

A company is awarded a contract to develop a product's manufacturing assembly line. The customer has concerns regarding a potential risk to a critical component. Which of the following will help the team move to the project's design phase?

A.Develop a prototype.

B.Perform benchmarking

C.Conduct a customer workshop.

D.Conduct Six Sigma analysis.

公司获得一项合同,开发一种产品的生产组装线。客户对一个关键组件的潜在风险十分担心。下列哪一项将帮助团队进入项目的设计阶段?

A.开发原型。

B.执行标杆对照。

C.召开客户研讨会。

D.开展六西格玛分析。

PMP答案解析:题干说客户对一个潜在风险十分担心,而“原型法”可以帮助减轻风险,并且也是收集需求的一种方法

PMP参考答案:A

PMP考试试题二

A project manager works on a US$3 million project which involves two suppliers. The project manager creates a statement of work(SOW) for each supplier
Which of the following needs SOW?

A.Risk management plan

B.Project charter

C.Procurement management plan

D.Supplier scope statement

项目经理正在管理价值300万美元,涉及两个供应商的项目。项目经理为每名供应商创建了一份工作说明书(SOW).下列哪一项需要SOW的信息

A.风险管理计划

B.项目章程

C.采购管理计划

D.供应商范围说明书

PMP答案解析:SOW是制定项目章程的输入

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试三个月来得及吗?
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
香港PMP考试地点在哪里?
青岛PMP考试地点在哪里?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库