PMP考试每天一练-2018年PMP考试试题90
PMP考试试题一: A project is delayed because one item in the equipment specification is obsolete. A replacement will require a longer lead time.To avoid this situation, the project manager should have done which of the following during project planning? A.Prepared a contingency plan B.Selected a more reliable supplier C.Spent more effort on the Identify Risks process D.Ensured that the item is not on the critical path 由于设备技术规范的某一项被淘汰,项目延期。更换将需要较长的交付实践。为避免这种情况,项目经理在项目规划期间应完成下列哪一项? A.制定应急计划 B.选择更为可靠的供应商 C.在识别风险过程上花费更多的精力 D.确保该项不在关键路径上 PMP答案解析:在识别风险过程上花费更多的精力,尽早识别风险,避免因更换导致项目延期。A是风险,B是减轻,D就算在非关键路径上一旦发生也可能会延期项目 PMP参考答案:C PMP考试试题二 Due to an increased rate of natural disasters along a flood plain, a warehouse director wants to initiate a project to review and update the disaster management plan. Which of the following should the project manager use to identify the project risks? A. Risk probability and impact assessment B. Brainstorming C. Risk rating and ranking D. Flowchart 由于洪泛平原沿线发生自然灾害的频率增加,仓库主任希望启动一个项目,审查和更新灾难管理计划。项目经理应该使用下列哪一项来识别项目风险? A.风险概率与影响评估 B.头脑风暴 C.风险评级和排序 D.流程图 PMP答案解析:信息收集技术头脑风暴,是识别风险的工具 PMP参考答案:B |