PMP考试每天一练-2018年PMP考试试题89
PMP考试试题一: Which of the following audits will be performed by the project management office to validate that the project is using the correct project management methodology? A.Compliance B.Performance C.Best practices D.Quality 下列哪一项审计将由项目管理办公室执行来核实项目是否使用正确的项目管理方法? A.合规性 B.绩效 C.最佳实践 D.质量 PMP答案解析:通过质量审计来确保使用了正确的流程,方法和政策 PMP参考答案:D PMP考试试题二 After approval of a project’s scope and specifications, the customer asks for the addition of a few minor deliverables to increase the final product’s value. What should the manager do next? A. Reject the change unless the customer agrees to increase the project budget B. Assess the impact of the change and issue a change request C. Ask the project team to confirm if these are minor changes and, if so, implement then D. Implement the changes to strengthen the relationship with the customer 批准项目范围和技术规范之后,客户要求增加一些次要可交付成果,提升最终产品的价值。项目经理下一步应该怎么做? A.拒绝变更,除非客户同意增加项目预算 B.评估变更的影响,并签发变更请求 C.要求项目团队确认是否属于次要变更,如果是,则实施这些变更 D.实施变更,加强与客户的关系 PMP答案解析:客户要求变更,应该遵循变更管理流程,先提出变更请求、然后评估变更影响 PMP参考答案:B |