PMP考试每天一练-2018年PMP考试试题89

转载者:PMP团购网      发布时间:2018/8/1        点击: 2668

PMP考试试题一:

Which of the following audits will be performed by the project management office to validate that the project is using the correct project management methodology?

A.Compliance

B.Performance

C.Best practices

D.Quality

下列哪一项审计将由项目管理办公室执行来核实项目是否使用正确的项目管理方法?

A.合规性

B.绩效

C.最佳实践

D.质量

PMP答案解析:通过质量审计来确保使用了正确的流程,方法和政策

PMP参考答案:D

PMP考试试题二

After approval of a project’s scope and specifications, the customer asks for the addition of a few minor deliverables to increase the final product’s value. What should the manager do next?

A. Reject the change unless the customer agrees to increase the project budget

B. Assess the impact of the change and issue a change request

C. Ask the project team to confirm if these are minor changes and, if so, implement then

D. Implement the changes to strengthen the relationship with the customer

批准项目范围和技术规范之后,客户要求增加一些次要可交付成果,提升最终产品的价值。项目经理下一步应该怎么做?

A.拒绝变更,除非客户同意增加项目预算

B.评估变更的影响,并签发变更请求

C.要求项目团队确认是否属于次要变更,如果是,则实施这些变更

D.实施变更,加强与客户的关系

PMP答案解析:客户要求变更,应该遵循变更管理流程,先提出变更请求、然后评估变更影响

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试难吗?
国内PMP考试通过率有多高?
PMP考试试题是什么样?
PMP考试题型是什么?
PMP考试内容是什么?
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?
青岛PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库