PMP考试试题一:

A project manager worked with stakeholders and sponsor to clarify project scope, refine costs and define the timelines. The project manager is ready to conduct a kick-off meeting to formally start the project.The project manager is in which of the following process groups?

A. Initiating

B. Executing

C. Monitoring & Controlling

D. Planning

项目经理与干系人和发起人一起澄清项目范围、完善成本并定义时间线。项目经理准备召开项目启动大会,正式启动项目。项目经理处于下列哪一个过程组?

A.启动

B.执行

C.监控

D.规划

PMP答案解析:kick-off meeting在规划过程组召开

PMP参考答案:D

PMP考试试题二

During project execution, the customer indicates that there will be limited access to the test facilities due to several concurrent projects. This change may lead to schedule delays.To minimize the negative impact, what should the project manager do next?

A.Advise the customer about schedule creep

B.Check the risk register for approved corrective actions

C.Perform a risk analysis

D.Update the project schedule according to this change

在项目执行期间,客户表示由于多个项目同时进行,对进入测试设施设置限制。这项变化可能导致进度延期。若尽可能减少负面影响,项目经理下一步应该怎么做?

A.通知客户进行潜变

B.查看风险登记册中已批准的纠正措施

C.执行风险分析

D.按照这项变化更新项目进度计划

PMP答案解析:题干说这项变化“可能”导致进度延期,说明这是一项风险。下一步应该对风险进行分析

PMP参考答案:C

阅读本文的人还阅读了:
PMP认证费用多少?
PMP认证多少钱?
PMP考试难吗?
国内PMP考试通过率有多高?
保定PMP考试地点在哪里?
杭州PMP考试地点在哪里?
苏州PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库