PMP考试试题一:

During the implementation phase, a project is terminated due to a company’s reorganization. The sponsor asks the project manager to formally close the project.What should the project manager do first?

A.Review the project risk management plan

B.Document the situation and communicate to stakeholders regarding next steps

C.Encourage stakeholders to negotiate with the sponsor

D.Collect and archive the project data in the project management information system

在实施阶段期间,项目由于公司的重组问题终止。项目发起人要求项目经理正式收尾项目。项目经理首先应该做什么?

A.审查项目风险管理计划

B.记录该情况,并就下一步措施与干系人沟通

C.鼓励干系人与发起人协商

D.收集并在项目管理信息系统中存档项目数据

PMP答案解析:项目提前终止,项目收尾

PMP参考答案:D

PMP考试试题二

A project manager prepares a fixed-price contract for a construction project. The project charter is approved, and the scope, schedule, and budget are completed.
Before the contract is signed, which of the following must be done?

A.Perform a risk analysis

B.Organize the kick-off meeting with the supplier

C.Create the project acceptance form

D.Draft the quality assurance plan

项目经理为一个施工准备了固定总价合同。项目章程已批准,而且项目范围、进度计划和均已完成。签署合同之前必须完成下列哪一项?

A.执行风险审计

B.组织召开与供应商一起的项目启动大会

C.创建项目验收单

D.起草质量保证计划

PMP答案解析:验收单中应包含检查和验收标准

PMP参考答案:C

阅读本文的人还阅读了:
广州PMP考试地点
PMP考试报名资格怎么审查?
PMP认证培训怎么选机构?
PMP培训机构是什么?
PMP认证考试需要准备什么?
PMP报名时间是哪天?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库