PMP考试试题一:

The conditions which allow a contract to be mutually ended prior to its completion are identified in which of the following?

A.Project management plan

B.Negotiated settlements

C.Termination clause

D.Statement of work

允许合同在完成之前由双方终止的条件称为下列哪一项?

A.项目管理计划

B.协商解决

C.终止条款

D.工作说明书

PMP答案解析:合同终止条款规定了双方对提前终止合同的权利和责任

PMP参考答案:C

PMP考试试题二

A project manager works on a project to retain a customer, s business. The quality team measures quality and identifies areas where the project fails to meet the requirements and specifications.Which of the following processes is the project’s quality team applying?

A. Perform Quality Assurance

B. Control Quality

C. Statistical and Variance Analyses

D. Plan Quality Management

项目经理正在从事一个保留客户业务的项目。质量团队测量质量,确定了项目未能满足要求和技术规范的一些方面。项目质量团队应用的是下列哪一个过程?

A. 实施质量保证

B. 控制质量

C. 统计和偏差分析

D. 计划质量管理

PMP答案解析:确定了项目未能满足要求和技术规范的一些方面,这是针对结果

PMP参考答案:B

阅读本文的人还阅读了:
PMP认证多少钱?
PMP考试难吗?
国内PMP考试通过率有多高?
PMP考试试题是什么样?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?
青岛PMP考试地点在哪里?
潍坊PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库