PMP考试每天一练-2018年PMP考试试题78
PMP考试试题一: A senior financial manager attends a project status meeting for the first time. What project information should the project manager share in the meeting? A.Updated project management plan B.Detailed cost and budgetary information C.Previous project status reports D.Standard project status report information 一名高级财务经理首次参加项目状态会议。项目经理应该在会议上分享说明项目信息? A.更新的项目管理计划 B.详细的成本和预算信息 C.之前的项目状态报告 D.标准项目状态报告信息 PMP答案解析:首次参加状态会议,最好是提供标准的项目状态报告信息给这位干系人 PMP参考答案:D PMP考试试题二 A project in the final stages of the execution phase has a schedule performance index of 0.9. A project team member submits a change request that impacts the project constraints, and the change control board approves it.What should the project manager do next? A.Notify the project team B.Update the change log C.Re-baseline the project D.Notify the stakeholders 一个处于执行阶段最终阶段的项目进度绩效指数为0.9.项目团队成员提交了一项影响项目制约因素的变更请求,变更控制委员已批准。项目经理接下来应该怎么做? A.通知项目团队 B.更新变更日志 C.重订项目基准 D.通知干系人 PMP答案解析:变更获得批准后,需要更新计划和基准 PMP参考答案:C |