PMP考试试题一:

A customer learns that a requirement will not be met unless a task that was not identified during planning is added to the project. A team fielder successfully executes the task and later inform the project manager during a weekly meeting. Despite the favorable outcome, the project manager is unhappy with this information, since the task did not have the necessary approval. What plan outlines the requirement for approval?

A.Risk management

B.Change management

C.Scope management

D.Cost management

客户意识到除非在项目中添加一项在规划期间未识别到的任务,否则将不满足要求。团队成员成功执行了这项任务,并在之后的一次周会上通知项目经理。即使是有利的结果,但项目经理对这个信息感到不满,因为任务没有得到必要的批准。哪一份计划概述了批准要求?

A.风险管理

B.变更管理

C.范围管理

D.成本管理

PMP答案解析:变更管理计划将对如何变更做出详细规定

PMP参考答案:B

PMP考试试题二

While acquiring resources for a strategic project, the project manager discovers that a key resource will not be available to perform a project task. Assuming the task on the critical path, what strategy should be used to mitigate this issue.

A.Attempt to reduce the project scope

B.Obtain permission to work on the weekends

C.Extend the project’s end-date and resolve the issue at a later project stage

D.Assign a less-skilled resource on the project and increase the task duration

在为一个战略项目招募资源时,项目经理发现一名关键资源将不能执行项目任务。假设该任务的计划不处于关键路径上,应使用什么战略来减轻这个问题?

A. 尝试减少项目范围

B. 获得在周末工作的许可

C. 延长项目结束日期并在项目后期解决该问题

D. 为项目分配一个技能略差的资源,并增加任务持续时间

PMP答案解析:如因制约因素(如经济因素或其他项目对资源的占用)而无法获得所需人力资源,在不违反法律、规章、强制性规定或其他具体标准的前提下,项目经理或项目团队可能不得不使用替代资源(也许能力较低)

PMP参考答案:D

阅读本文的人还阅读了:
PMP认证考试需要准备什么?
PMP报名时间是哪天?
PMP考点在哪里?
PMP认证费用多少?
PMP认证多少钱?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?
杭州PMP考试地点在哪里?
苏州PMP考试地点在哪里?
无锡PMP考试地点在哪里?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库