以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2018年PMP考试试题75

转载者:PMP团购网      发布时间:2018/7/2        点击: 2747

PMP考试试题一:

A new project manager works on a project that involves the purchasing of machinery. A colleague worked with the same supplier on a similar project that had a major issue that delayed the machinery delivery. The project manager meets with the colleague to ask about related issue with the supplier.What activity is the project manager performing?

A.Plan Procurements

B.Plan Risk Management

C.Shortlist Supplier

D.Plan Schedule

新项目经理管理一个涉及机械采购的项目。一名同事曾经在类似项目上同一个供应商合作过,而该类似项目发生了一个重大问题,延迟了机械交付。项目经理与该同事会面询问该供应商有关问题。项目经理执行的是哪项活动?

A.规划采购

B.规划风险管理

C.列出供应商清单

D.规划进度

PMP答案解析:规划采购管理包括如何识别预审合格的卖方

PMP参考答案:A

PMP考试试题二

A developer assigned to a task with a 10-day duration completes 50% of the task. During a weekly status review session, the project manager discovers a team member wants to work overtime for three day to complete the task.What is the task’s earned value?

A.7 days

B.6.25 days

C.5 days

D.4 days

分配到一个为期10天任务的开发人员完成了50%的任务。在每周状态评审会上,项目经理发现团队成员希望加班工作三天来完成。该任务该任务的挣值是多少?

A.7天

B.6.25天

C.5天

D.4天

PMP答案解析:50%*10=5天

PMP参考答案:C

阅读本文的人还阅读了:
PMP考试报名费是多少?
PMP考试时间一年有几次?
PMP考试时间具体是什么?
PMP考试报名时间是什么?
PMP教材是什么?
PMP认证考试的报名条件?
PMP是什么?
PMP考试有什么科目?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库