PMP考试试题一:

A project member does not get along with the rest of the team, and the Project manager constantly receives complaints from other team members. However, the project manager believes that this member is a top performer and that the issue will not affect the schedule.

A.Ask team members to resolve the issue on their own.

B.Encourage the team member to improve their attitude.

C.Nothing, as it will not affect the schedule.

D.Replace the team member.

项目组的其中一位项目成员与其他项目成员都不能和睦相处,并且项目经理不断收到其他成员对该成员的投诉。但项目经理认为该成员的工作能力很好,并且该问题也没有对项目进展造成影响。请问项目经理应该如何解决此问题?

A让成员自己解决内部的问题。

B.找该成员谈话,提醒他修正自己的问题。

C.不做任何处理,因为没有影响项目进度。

D.替换掉该成员,因为已经造成了团队不稳定。

PMP答案解析:B

PMP参考答案:根据题意,已经有其它成员投诉,如果选择A、C解决方法是消极;选择D,过于直接,没有做多标准决策。最好的选择是B,PM与该成员进行正式的口头沟通谈话

PMP考试试题二

After negotiation with resource manager, project manager develops the project management plan. In the kick off meeting, resource manager says the resource only can be available in the late state of project period, what should the project manager do next?

A.Add the resource risk into risk register

B.Record the change, review and update the project management plan

C.Communicate the resource availability delay and manage the stakeholder participation levels

D.Do not take any action, since the issue has been discussed in the kick off meeting

在于资源经理协商之后,项目经理制定项目管理计划。在项目启动大会上,资源经理称一名资源在进度计划后期才可用。项目经理下一步该怎么做?

A.在风险登记册中添加该资源风险

B.记录该变更,并审查和更新项目管理计划

C.在资源可用性中沟通该延迟,并管理干系人的参与水平

D.不采取其他行动,因为该问题已在项目启动大会上讨论过了

PMP答案解析:题干说:“资源经理称一名资源在进度计划后期才可用。”英文是:“the resource only can be available in the late state of project period”这是确定的,而不是will、to be,这是确定的,不是风险。排除A

阅读本文的人还阅读了:
PMP考试试题是什么样?
PMP考试题型是什么?
PMP考试内容是什么?
PMP考试有题库吗?
PMP考试报名费是多少?
北京PMP考试地点在哪里?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库