PMP考试试题一:

During project execution, the marketing team tests the first version of a new sales application. During testing, the team determines that a regional sales report is based on incorrect business logic and requires a fix which could impact the duration of the testing phase What should the project manager do next?

A.Maintain the planned activities against the schedule

B.Update the project management plan

C.Ask for additional funds to mitigate the impact of the delay

D.Document and submit a change request

在项目执行期间,营销团队测试了一个新销售应用程序的第一版。在测试期间,团队确定地区销售报告是基于不正确的业务逻辑,需要修复,这可能影响测试阶段的持续性。项目经理接下来应该怎么做?

A.按进度计划保持计划活动

B.更新项目管理计划

C.要求额外的资金来减轻延期影响

D.记录并提交变更请求

PMP答案解析:修复缺陷属于变更请求的一种

PMP参考答案:D

PMP考试试题二

After receiving a customer’s change request, the project team performs an impact analysis and the change control board approves the request. After delivery, the customer finds that the change request’s implementation overlooked some baseline deliverables.What could be the root cause of this issue?

A.The change control board cannot authorize the change, as it does not have adequate knowledge of the change request

B.The quality control was ineffective

C.The change control system was not integrated with the configuration control system

D.The project schedule was not updated

收到客户的变更请求后,项目团队执行了影响分析,且变更控制委员会批准了该请求。交付后,客户发现变更请求的执行忽略了一些基准可交付成果。该问题的根本原因是什么?

A.变更控制委员会不能授权变更,因为它对变更请求没有足够的了解

B.质量控制无效

C.变更控制系统未与配置控制系统相结合

D.项目进度未更新

PMP答案解析:变更请求应该由变更控制系统和配置控制系统中规定的过程进行处理

PMP参考答案:C

阅读本文的人还阅读了:
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?
青岛PMP考试地点在哪里?
高中或以下学历可以考PMP吗?
大专可以考PMP吗?
英语不好可以考PMP吗?
PMP证书与学历挂钩吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库