以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2018年PMP考试试题57

转载者:PMP团购网      发布时间:2018/5/25        点击: 4450

PMP考试试题一:

A company wins a new project, half of which involves an area with which the company is unfamiliar. The project manager identifies the need to hire a subcontractor. What should the project manager do next?

A.Develop a procurement plan

B.Meet with experts to create a procurement plan.

C.Plan procurement management.

D.Prepare the framework for a fixed-price contract.

公司赢得了一个新项目,其中50%的交付部分不是公司熟悉的领域,需要引入分包商。作为项目经理该怎么做?

A、制定采购工作说明书

B、召集专家讨论,决定采购方案

C、规划采购管理

D、着手准备一个固定总价的合同框架。

PMP答案解析:C参考答案包括了 A、B、D

PMP参考答案:C

PMP考试试题二

During a review of a manufacturer’s insurance documents, a project manager discovers that le project site is not covered in the event of a natural disaster. Which of the following should protect the company’s interests?

A. Updating the risk management plan for further reference

B. Informing the project sponsor and renegotiating with the insurance provider

C. Renegotiating with the insurance to transfer the financial risk

D. Adding a risk register item and outing the implications

审查制造商的保险文件时,项目经理发现并未投保项目现场的自然灾害保险。下列哪一项将会保护公司的利益?

A. 更新风险管理计划,以供后续参考

B. 通知项目发起人,并与保险公司重新协商

C. 与保险公司重新协商,转移财产风险

D. 将其作为一项风险添加进风险登记册,并概述其影响

PMP答案解析:为了保护公司的利益,最好上报发起人

PMP参考答案:B

阅读本文的人还阅读了:
香港PMP考试地点在哪里?
青岛PMP考试地点在哪里?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
PMP考试报名怎么做?
国内PMP考试通过率有多高?
PMP考试有题库吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库