PMP考试每天一练-2018年PMP考试试题54

转载者:PMP团购网      发布时间:2018/5/18        点击: 3719

PMP考试试题一:

To achieve competitive market advantage, a project sponsor requests delivery of a product three months ahead of schedule. What should the project manger do next?

A. Implement overall change control.

B. Update the project management plan.

C. Exert influence on the factors that led to the schedule change.

D. Submit a change request.

因为新产品的早发布有利于先于竞争对手抢占市场,项目发起人要求交付时间提早三个月。项目经理接下来应该怎么做?

A.实施整体变更控制。

B.更新项目管理计划。

C.对引起进度变更的因素施加影响。

D.提出变更请求。

PMP答案解析:在参考答案A与C之间,推荐A参考答案,整体变更控制的全流程包括D参考答案

PMP参考答案:A

PMP考试试题二

A bicycle company releases a new line of baskets with a five-year warranty. The material withstands extreme weather conditions. The product is well received by customers and is considered top of the line the design is basic with no additional features。Which of the following describes this product?

A.High grade, high quality

B.Low grade, low quality

C.High grade, low quality

D.Low grade, high quality

一家自行车公司发布了一款拥有五年质保期的新车蓝系列。材料能抵御极端天气条件。产品广受用户接受,且视为是系列中的顶级产品。产品只有基本设计,无额外功能。下列哪一项是该产品的描述?
A.高档、高质
B.低档、低质
C.高档、低质
D.低档、高质

PMP答案解析:产品只有基本设计,无额外功能,说明低档。但是功能强大,说明高质量

PMP参考答案:D

阅读本文的人还阅读了:
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?
珠海PMP考试地点在哪里?
东莞PMP考试地点在哪里?
保定PMP考试地点在哪里?
杭州PMP考试地点在哪里?
PMP考试费是多少?
2018年PMP考试费用多少?
2018年PMP考试时间?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库