PMP考试每天一练-2018年PMP考试试题40

转载者:PMP团购网      发布时间:2018/4/18        点击: 3321

PMP考试试题一:

A newly hired project manager reviews the project charter and finds that some stakeholders may not have been included. How should the new project manager validate the stakeholder register?

A.Identify only the people who are actively involved with the project

B.Identify anyone who is involved, or has an interest in the project

C.Include only the people who have a major interest in the project

D.Include the company’s executive management

一名新雇佣的项目经理审查项目章程时发现可能未将一些干系人包括在内。新项目经理应该如何核实干系人登记册?

A.仅识别主动参与项目的人员

B.识别参与项目或在项目中享有利益的任何人

C.仅包含在项目中享受重大利益的人员

D.包含公司的高级管理层

PMP答案解析:ACD太片面了

PMP参考答案:B

PMP考试试题二

Before finalizing the project management plan, a project manager considers alternative ways to document relationships among project activities, What tool should the project to outline the sequence of activities?

A. Work breakdown structure

B. RACI chart

C. Activity lists

D. Project network diagram

在最终确定项目管理计划之前,项目经理考虑记录项目活动之间关系的替代方案。项目经理应使用什么工具描述活动顺序?

A. 工作分解结构

B. RACI图

C. 活动清单

D. 项目网络图

PMP答案解析:题目问的是什么“工具”描述活动顺序,但是四个选项都不是工具。那就理解为:下列哪一项能够描述活动顺序?

PMP参考答案:D

阅读本文的人还阅读了:
青岛PMP考试地点在哪里?
潍坊PMP考试地点在哪里?
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?
成都PMP培训哪个好?几大热门成都PMP培训机构对比
西安PMP培训哪个好?几大热门西安PMP培训机构对比
北京PMP考试地点在哪里?
上海PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库