PMP考试每天一练-2018年PMP考试试题31

转载者:PMP团购网      发布时间:2018/3/30        点击: 3138

PMP考试试题一:

During project closure, a vendor did not fulfill a contractual obligation to submit mandatory documentation, which leads to a dispute. What should the project manager do to settle the dispute with the vendor?

A.Leverage gain-sharing

B.Record the dispute in the project documents

C.Settle the dispute in a court of law

D.Seek alternate dispute resolutions

在项目收尾期间,供应商未履行提交强制性文档的合同义务,最终导致纠纷。若要解决与供应商的纠纷,项目经理应该怎么做?

A.利用收益分享

B.在项目文件中记录该纠纷

C.在法院中解决该纠纷

D.采取其他纠纷解决方案

PMP答案解析:若要解决纠纷有三个方法,顺序为: 1、友好协商:比如谈判。 2、ADR 替代争议解决:比如调解、仲裁。 3、诉讼

PMP参考答案:D

PMP考试试题二

During the project execution phase, a project manager learns that the customer’s organization could be acquired by another organization. What should the project manager do next?

A.Revisit the project charter

B.Perform a risk reassessment

C.Ask for the project sponsor’s guidance

D.Discuss the issue with stakeholders

在项目执行阶段,项目经理了解到客户所在组织可能被另一个组织收购。项目经理下一步该怎么做?

A.查看项目章程

B.执行风险再评估

C.寻求项目发起人的知道

D.与干系人讨论这个问题

PMP答案解析:客户所在组织可能被另一个组织收购,风险较大,需要对风险再评估

PMP参考答案:B

阅读本文的人还阅读了:
PMP退考费多少?
PMP认证抽审流程是什么?
PMP考试是什么?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库