PMP考试每天一练-2018年PMP考试试题31
PMP考试试题一: During project closure, a vendor did not fulfill a contractual obligation to submit mandatory documentation, which leads to a dispute. What should the project manager do to settle the dispute with the vendor? A.Leverage gain-sharing B.Record the dispute in the project documents C.Settle the dispute in a court of law D.Seek alternate dispute resolutions 在项目收尾期间,供应商未履行提交强制性文档的合同义务,最终导致纠纷。若要解决与供应商的纠纷,项目经理应该怎么做? A.利用收益分享 B.在项目文件中记录该纠纷 C.在法院中解决该纠纷 D.采取其他纠纷解决方案 PMP答案解析:若要解决纠纷有三个方法,顺序为: 1、友好协商:比如谈判。 2、ADR 替代争议解决:比如调解、仲裁。 3、诉讼 PMP参考答案:D PMP考试试题二 During the project execution phase, a project manager learns that the customer’s organization could be acquired by another organization. What should the project manager do next? A.Revisit the project charter B.Perform a risk reassessment C.Ask for the project sponsor’s guidance D.Discuss the issue with stakeholders 在项目执行阶段,项目经理了解到客户所在组织可能被另一个组织收购。项目经理下一步该怎么做? A.查看项目章程 B.执行风险再评估 C.寻求项目发起人的知道 D.与干系人讨论这个问题 PMP答案解析:客户所在组织可能被另一个组织收购,风险较大,需要对风险再评估 PMP参考答案:B |