PMP考试试题一:

During project implementation, several defects are found which creates a risk for the completion of the next milestone. However, the contingency reserve remains unaffected. Some team members believe if the primary issue is identified and resolved, the majority of the defects will be fixed.Which of the following tools should the project manager use next?

A.Cause and effect diagram

B.Affinity diagram

C.Scatter diagram

D.Histograms

在项目实施期间发现多个缺陷,这对完成下一个里程碑造成风险。然而,应急储备却未受影响。一些团队成员认为如果已经识别并解决主要问题,大部分缺陷将得到解决。接下来,项目经理应该使用哪一项工具?

A.因果图

B.亲和图

C.散点图

D.直方图

PMP答案解析:多个缺陷中要识别并解决主要问题,应该使用直方图

PMP参考答案:D

PMP考试试题二

A project sponsor and a project manager are developing a project charter for a new en There are several plant locations under consideration, which could influence project co To select the most appropriate location, which of the following should the project sp Project manager work on first?

A.Business need

B.Project scope statement

C.Project budget

D.Business case

项目发起人和项目经理正在为新的能源厂制定项目章程。有多个厂址可供考虑,但可能影响项目成本。若要选择最合适的厂址,项目发起人和项目经理必须首先执行下列哪一项工作?

A.商业需求

B.项目范围说明书

C.项目预算

D.商业论证

PMP答案解析:商业论证,制定项目章程的输入:从商业角度论证项目是否值得投资

PMP参考答案:D

阅读本文的人还阅读了:
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?
PMP退考需要什么条件?
PMP退考费多少?
PMP认证抽审流程是什么?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库