PMP考试每天一练-2018年PMP考试试题29
PMP考试试题一: During project implementation, several defects are found which creates a risk for the completion of the next milestone. However, the contingency reserve remains unaffected. Some team members believe if the primary issue is identified and resolved, the majority of the defects will be fixed.Which of the following tools should the project manager use next? A.Cause and effect diagram B.Affinity diagram C.Scatter diagram D.Histograms 在项目实施期间发现多个缺陷,这对完成下一个里程碑造成风险。然而,应急储备却未受影响。一些团队成员认为如果已经识别并解决主要问题,大部分缺陷将得到解决。接下来,项目经理应该使用哪一项工具? A.因果图 B.亲和图 C.散点图 D.直方图 PMP答案解析:多个缺陷中要识别并解决主要问题,应该使用直方图 PMP参考答案:D PMP考试试题二 A project sponsor and a project manager are developing a project charter for a new en There are several plant locations under consideration, which could influence project co To select the most appropriate location, which of the following should the project sp Project manager work on first? A.Business need B.Project scope statement C.Project budget D.Business case 项目发起人和项目经理正在为新的能源厂制定项目章程。有多个厂址可供考虑,但可能影响项目成本。若要选择最合适的厂址,项目发起人和项目经理必须首先执行下列哪一项工作? A.商业需求 B.项目范围说明书 C.项目预算 D.商业论证 PMP答案解析:商业论证,制定项目章程的输入:从商业角度论证项目是否值得投资 PMP参考答案:D |