PMP考试试题一:

A project manager assesses the economics of a discretionary change in project scope by evaluating its impact on the project's value. Where should the project manager find the discount rate for this calculation?

A. Project funding requirements

B. Cost management plan

C. Project charter

D. Lessons learned

项目经理通过评估项目范围中的一项自由变更对项目价值的影响来评估该变更的经济意义。项目经理应从哪里找到这项计算的折现率?

A.项目资金需求

B.成本管理计划

C.项目章程

D.经验教训

PMP答案解析:成本管理计划给出作为成本管理的方法论及相关要求,包括折现率等

PMP参考答案:B

PMP考试试题二

Internal conflicts among some team members could potentially delay the project, What should the project manager do next?

A. Address the conflicts early and privately

B. Delay the conflict to assess if it will affect the project at a later stage

C. Escalate the conflict to the functional managers

D. Consult the human resource management plan and take corrective actions

一些团队成员的内部冲突可能延迟项目。项目经理下一步该怎么做?

A.提前并私下解决冲突

B.延迟冲突,评估其是否将会在后期影响项目

C.将冲突上报给职能经理

D.查看人力资源管理计划并采取纠正措施

PMP答案解析:冲突的首选解决方法是依靠冲突的当事人自己解决

PMP参考答案:A

阅读本文的人还阅读了:
苏州PMP培训哪个好?几大热门苏州PMP培训机构对比
成都PMP培训哪个好?几大热门成都PMP培训机构对比
西安PMP培训哪个好?几大热门西安PMP培训机构对比
PMP考试是什么?
什么是PMP认证?
pmp是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库