PMP考试每天一练-2018年PMP考试试题25
PMP考试试题一: During the early phases of a project, the project manager realizes that the project budget is dependent on the price of raw materials. What should the project manager do next? A.Update the scope statement B.Buy the raw materials before prices increase C.Update the risk register D.Ask for a change request 在项目早期阶段,项目经理意识到项目预算取决于原材料的价格。项目经理接下来应该怎么做? A.更新范围说明书 B.在价格上涨之前采购原材料 C.更新风险登记册 D.要求变更请求 PMP答案解析:“项目预算取决于原材料的价格”说明具有一定的不确定性,这是风险 PMP参考答案:C PMP考试试题二 The project manager plans to purchase concrete for a building construction project, the quality of the materials is consistent among all vendors, leaving price as the major difference.Which type of vendor response should the project manager request? A.Request for information B.Request for proposal C.Statement of work D.Request for quotation 项目经理计划为一个建设施工项目采购混凝土。所有供应商的材料质量都一样,只有价格有主要区别。项目经理应向供应商请求那种应对类型 A.信息请求 B.建议邀请书 C.工作说明书 D.报价邀请书 PMP答案解析:题干说供应商的材料质量都一样,只有价格有区别,选报价邀请书 PMP参考答案:D |