PMP考试每天一练-2018年PMP考试试题25

转载者:PMP团购网      发布时间:2018/3/16        点击: 3408

PMP考试试题一:

During the early phases of a project, the project manager realizes that the project budget is dependent on the price of raw materials. What should the project manager do next?

A.Update the scope statement

B.Buy the raw materials before prices increase

C.Update the risk register

D.Ask for a change request

在项目早期阶段,项目经理意识到项目预算取决于原材料的价格。项目经理接下来应该怎么做?

A.更新范围说明书

B.在价格上涨之前采购原材料

C.更新风险登记册

D.要求变更请求

PMP答案解析:“项目预算取决于原材料的价格”说明具有一定的不确定性,这是风险

PMP参考答案:C

PMP考试试题二

The project manager plans to purchase concrete for a building construction project, the quality of the materials is consistent among all vendors, leaving price as the major difference.Which type of vendor response should the project manager request?

A.Request for information

B.Request for proposal

C.Statement of work

D.Request for quotation

项目经理计划为一个建设施工项目采购混凝土。所有供应商的材料质量都一样,只有价格有主要区别。项目经理应向供应商请求那种应对类型

A.信息请求

B.建议邀请书

C.工作说明书

D.报价邀请书

PMP答案解析:题干说供应商的材料质量都一样,只有价格有区别,选报价邀请书

PMP参考答案:D

阅读本文的人还阅读了:
PMP考试费是多少?
2018年PMP考试费用多少?
2018年PMP考试时间?
北京PMP考试地点在哪里?
上海PMP考试地点在哪里?
PMP报考条件和PMP报考流程
PMP考试监考机构和报名机构
北京PMP培训团购

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库