PMP考试每天一练-2018年PMP考试试题22
PMP考试试题一: An ongoing project is on schedule when a subject matter expert (SME) on the project's critical path requests three days off, what should the project manager do? A. Initiate a change request through performs integrated change control process. B. Send a change request to the change control board (CCB) for approval. C. Persuade the SME to work as planned; if unsuccessful, update the project management plan. D. Identify this as a resource risk that is out of control, and update the risk register. 一个正在进行的项目正按进度计划进行,这时一名在项目关键路径上的主题专家(SME)请求请三天假。项目经理应该怎么做? A.通过执行整体变更控制过程提出变更请求。 B.向变更控制委员会(CCB)发送一份变更请求批准。 C.说服SME按计划工作:如果不成功,则更新项目管理计划。 D.将其识别为失控的资源风险,更新风险登记册。 PMP答案解析:关键路径上的资源变更可能引起进度基准的变更,这是个风险。先查看有无应急储备,如果实在没办法才提变更 PMP参考答案:D PMP考试试题二 After project implementation, the project management office (PMO) inquires whether the project’s business objective was achieved. To address the question, what should the project manager do? A. Conduct a customer satisfaction survey B. Review the project charter with the project sponsor C. Conduct a variance analysis D. Conduct a post-project review 项目实施后,项目管理办公室(PMO)询问是否已实现项目的商业目标。若要解决这个问题,项目经理应该怎么做? A.开展客户满意度调查 B.与项目发起人一起审查项目章程 C.执行偏差分析 D.进行项目后评价 PMP答案解析:项目章程中有可衡量的目标 PMP参考答案:B |