PMP考试每天一练-2018年PMP考试试题22

转载者:PMP团购网      发布时间:2018/3/9        点击: 5505

PMP考试试题一:

An ongoing project is on schedule when a subject matter expert (SME) on the project's critical path requests three days off, what should the project manager do?

A. Initiate a change request through performs integrated change control process.

B. Send a change request to the change control board (CCB) for approval.

C. Persuade the SME to work as planned; if unsuccessful, update the project management plan.

D. Identify this as a resource risk that is out of control, and update the risk register.

一个正在进行的项目正按进度计划进行,这时一名在项目关键路径上的主题专家(SME)请求请三天假。项目经理应该怎么做?

A.通过执行整体变更控制过程提出变更请求。

B.向变更控制委员会(CCB)发送一份变更请求批准。

C.说服SME按计划工作:如果不成功,则更新项目管理计划。

D.将其识别为失控的资源风险,更新风险登记册。

PMP答案解析:关键路径上的资源变更可能引起进度基准的变更,这是个风险。先查看有无应急储备,如果实在没办法才提变更

PMP参考答案:D

PMP考试试题二

After project implementation, the project management office (PMO) inquires whether the project’s business objective was achieved. To address the question, what should the project manager do?

A. Conduct a customer satisfaction survey

B. Review the project charter with the project sponsor

C. Conduct a variance analysis

D. Conduct a post-project review

项目实施后,项目管理办公室(PMO)询问是否已实现项目的商业目标。若要解决这个问题,项目经理应该怎么做?

A.开展客户满意度调查

B.与项目发起人一起审查项目章程

C.执行偏差分析

D.进行项目后评价

PMP答案解析:项目章程中有可衡量的目标

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试是什么?
什么是PMP认证?
pmp是什么?
苏州PMP培训哪个好?几大热门苏州PMP培训机构对比
成都PMP培训哪个好?几大热门成都PMP培训机构对比
西安PMP培训哪个好?几大热门西安PMP培训机构对比

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库