PMP考试试题一:

After a review of a company’s completed project, the company learns the integrity of the data could not be sufficiently verified. Which of the following should have helped to avoid this issue?

A.Lessons learned

B.Quality audit

C.Project scope management

D.Proper document archiving

在审查一家公司的已完成项目后,公司认识到数据的完整性不能得到充分合适。下列那一项对避免这个问题有帮助?

A.经验教训

B.质量审计

C.项目范围管理

D.正确的文档存档

PMP答案解析:数据不完整说明文件、文档有缺失,要避免这个问题需要进行正确的文件归档。

PMP参考答案:D

PMP考试试题二

To date, the project has been progressing smoothly. A new project manager is assigned and there is a disagreement with a vendor on the amount and price of the work completed.Which document should the project manager consult to determine work to be completed?

A.Statement of work

B.Negotiated contract

C.Procurement plan

D.Notice to proceed

到目前为止,项目进展顺利。任命了一名新项目经理,与供应商对已完成工作的金额和价格存在分歧。项目经理应查阅哪一份文件确定已完成的工作

A.工作说明书

B.协商合同

C.采购计划

D.继续进行的通知

PMP答案解析:合同中包括了工作说明书或可交付成果描述

PMP参考答案:B

阅读本文的人还阅读了:
PMP认证抽审流程是什么?
PMP考试是什么?
什么是PMP认证?
北京PMP考试地点在哪里?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库