PMP考试每天一练-2018年PMP考试试题20
PMP考试试题一: A new building project finished, and the project team is awaiting the certificate of occupancy. The team must provide all building documentation. Where is this documentation included? A. Enterprise environmental factors B. Configuration management C. Corporate knowledge base D. Closed procurements 一个新的建筑项目完成后,项目团队正在等待入住证明,团队必须提供所有建筑文档。下面哪一项是这个文档要包括的? A. 事业环境因素 B. 配置管理 C. 企业知识库 D. 已收尾的采购 PMP答案解析:本题表述不够完整,4个参考答案中, BCD都是属于项目文档,是题意最相关的推荐为D PMP参考答案:D PMP考试试题二 A new project manager assigned during a project’s execution phase must meet with the project stakeholders. What should the project manager do to determine who the key stakeholders are? A. Review the stakeholder register and the available project date B. Request the project charter C. Refer to the risk register D. Use interviewing techniques 一名在项目执行阶段任命的新项目经理必须与项目干系人开会。若要确定哪些干系人是关键干系人,项目经理应该怎么做? A.审查干系人登记册以及可用的项目数据 B.请求项目章程 C.查阅风险登记册 D.使用访谈技术 PMP答案解析:干系人登记册是识别干系人过程的主要输出,用于记录已识别的干系人的所有详细信息 PMP参考答案:A |