PMP考试试题一:

To increase trust and improve interpersonal relationships, the project manager of virtual team schedules an off-site building activity. However, due to a scheduling conflict, a key team member cannot attend the activity.To avoid this conflict, what should the project manager have reviewed?

A.Project staff assignment

B.Resource calendar

C.Project schedule

D.Project organization chart

为提高信任度和改善人际关系,一个虚拟团队的项目经理安排了一次非现场团队的建设活动。然而,由于进度冲突,一名关键团队成员不能参加活动。为避免这个冲突,项目经理应已经审查那些内容?

A.项目人员配备

B.资源日历

C.项目进度

D.项目组织图

PMP答案解析:资源日历包含资源的工作时间和非工作时间。

PMP参考答案:B

PMP考试试题二

A functional manager participates in the kick-off meeting for a project to implement a new accounting system. After resources from the group are scheduled to begin the project task one month later, the functional manager reassigns the resources to another project in the company.The project manager attempts to contact the functional manager but receives no response.Which of the following management skills should the project manager use first?

A.Resolve the conflict

B.Facilitate a consensus toward project objectives

C.Influence people to support the project

D.Overcome resistance to change

职能经理参加了一个实施新会计系统的项目启动大会,并安排组织内的资源在一个月后开始项目任务,职能经理又将这些资源分配给公司内的另一个项目。项目经理尝试联系职能经理,但没有收到任何回应。项目经理首先应该使用下列哪一项管理技能?

A.解决冲突

B.促进对项目目标达成一致同意

C.影响人员支持项目

D.克服阻力改变

PMP答案解析:资源分配发生了冲突,需要解决冲突。

PMP参考答案:A

阅读本文的人还阅读了:
PMP考试是什么?
什么是PMP认证?
pmp是什么?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库