以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2018年PMP考试练习题16

转载者:PMP团购网      发布时间:2018/2/23        点击: 3433

PMP考试练习题一:

After the identification of a technical risk, the project manager decides to hire a senior resource to join the project team. What risk response strategy does the project manager use?

A.Mitigate

B.Identify

C.Accept

D.Expert judgment

在识别完一项技术风险后,项目经理决定雇佣一名高级资源加入项目团队。项目经理使用的是什么风险应对策略?

A.减轻

B.识别

C.接受

D.专家判断

PMP答案解析:雇佣更高级的资源,这是减轻。

PMP参考答案:A

PMP考试练习题二:

A project manager is managing a US$5 million fixed-price project that has had many changes to the scope. As a part of the business requirements session, the business architect identifies a change that will involve 100 hours of additional requirements analysis.To document the change, the business architect should create which of the following?

A. Project document updates, work performance information, and project management plan updates

B. Project document updates, change request, and scope baseline

C. Change request, team performance assessments, and project management plan updates

D. Organizational process assets updates, communications management plan, and change request

项目经理正在管理一个价值500万美元的固定总价项目,该项目对范围做了许多变更。作为业务需求会的组成部分,业务架构师确定了一项变更,该变更将涉及100小时的额外需求分析。
为了记录这项变更,业务架构师应创建下列哪一项?

A.项目文件更新,工作绩效信息和项目管理计划更新

B.项目文件更新,变更请求和范围基准

C.变更请求,团队绩效评估和项目管理计划更新

D.组织过程资产更新,沟通管理计划和变更请求

PMP答案解析:和变更有关的,只有B选项合适。

PMP参考答案:B

阅读本文的人还阅读了:
PMP认证抽审流程是什么?
PMP考试是什么?
什么是PMP认证?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库