PMP考试每天一练-2018年PMP考试试题1
PMP考试试题一: A software company develops a new version of a software that contains several new enhancements. The development team, who also developed the last version, is confident that the project can be completed in time without testing and sending the product to the market.What is the cost to the project for not performing testing on the software? A.cost of non-conformance B.cost of conformance C.cost of compliance D.cost of non-compliance 软件公司开发一款软件的新版本,包含多个新的改进。开发团队也开发过上一个版本,对项目可以在不进行测试的情况下按时完工并将产品投放到市场非常有自信。不对软件执行测试属于哪一项项目成本? A.非一致性成本 B.一致性成本 C.合规成本 D.不合规成本 PMP答案解析:不对软件测试的情况下按时完工非常有自信,肯定不是非一致性成本,反推选择B。 PMP参考答案:B PMP考试试题二: A network diagram shows that the earliest an activity could start is at the end of week 7 and that it must be completed by the start of week 20. The activity requires a total of 10 business days to complete. In terms of weeks, what is the float for the performance of this activity? A. 3 B. 10 C. 13 D. 17 网络图显示,某项活动的最早开始时间是在第7周结束时,并且必须在第20周开始之前完成。这项活动总共需要10个工作日完成。那么这项活动绩效的浮动时间是多少周? A.3 B.10 C.13 D.17 PMP答案解析:参见自由浮动时间的计算方法[示例:活动A(7-9)活动B(20----),则A 的自由浮动为20-9-1] PMP参考答案:B |