PMP考试每天一练--PMP考试试题200
PMP考试试题一: Which process is integration management performed? A. Project planning B. Project executing C. At key interface points D. At the end of each project management phase 项目整合管理应该发生在哪个阶段? A. 项目规划阶段 B. 项目执行阶段 C. 在关键接口点 D. 在项目管理的每个阶段结束 PMP答案解析:项目整合管理引言 P63 PMP参考答案:C PMP考试试题二: A company defines a high level description of a new project. What should the project manager do to develop the project scope? A. direct the project team to collect technical requirements B. takes no action, as the project manager is not yet assigned to the project C. agree with the project sponsor regarding the budget assigned to the project D. conduct working sessions with the customer to better understand project expectations 一家公司定义一个新项目的高层次描述。为了制定项目范围,项目经理应该怎么做? A. 指示项目团队收集技术需求 B. 不采取任何行动,因为项目经理还未任命到项目上 C. 就分配到项目的预算方面与项目发起人达成一致意见 D. 与客户召开工作会议,以便更好地理解项目期望 PMP答案解析:理解项目期望才能明确范围边界、定义高层次范围。 PMP参考答案:D |