PMP考试每天一练--PMP考试试题199

转载者:PMP团购网      发布时间:2018/1/15        点击: 2417

PMP考试试题一:

A company wants to proceed with a new financial application. After completing the make-or-buy analysis, the company reviews all vendor proposals and selects one vendor.What is the next task required to proceed with the project ?

A.create a risk procurement plan

B.appeal management’s decision to outsource the project

C.conduct contract negotiations

D.document the change request

公司希望进行一个新的财务应用程序。完成自制或外购分析之后,公司审查了所有供应商的建议书并选择了其中一家供应商。继续进行项目的下一个任务是什么?

A.创建一份风险采购计划

B.对管理层外包项目的决定进行申诉

C.进行合同谈判

D.记录更新请求

PMP答案解析:选定了供应商之后开始谈判、签合同。

PMP参考答案:C

PMP考试试题二:

About midway through the project, the project manager learns that most members of the project team are not reviewing the weekly project updates. What
should the project manager do?

A. Create a signature log so team members can indicate when they have read the project updates.

B.Revise the communications management plans appropriately to meet the informational needs of the stakeholders.

C.Improve the layout of the weekly project updates to encourage reading by team members.

D.Require the reading of the project updates in order to receive any rewards on the project.

项目执行过程中,项目经理发现大部分团队成员不去参考每周项目更新的内容。项目经理应该怎么做?

A. 制定一个签名日志,这样可以显示团队成员何时阅读了项目更新的内容

B. 适当地修改沟通管理计划,以满足干系人对信息的需求

C.改善每周项目更新内容的排版涉及,以鼓励团队成员阅读

D. 强行他们阅读,以便得到奖励

PMP参考答案:B

阅读本文的人还阅读了:
PMP考试费是多少?
2018年PMP考试费用多少?
2018年PMP考试时间?
2018年PMP考试时间安排
PMP考试是什么?
什么是PMP认证?
pmp是什么?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库