PMP考试试题一:

All project deliverables are completed according to the customer’s expectations. The project manager is assigned to a new project with aggressive timelines.What should the project manager do next?

A.archive all project documentation

B.complete a financial analysis of the project and communicate any variance to stakeholders

C.obtain financial, legal, and administrative closure using generally accepted practices

D.move onto the new project immediately

所有项目可交付成果均已按照客户期望完成。项目经理被分配管理一个工期紧的新项目。项目经理接下来应该怎么做?

A.将所有项目文档存档

B.完成项目的财务分析,并与干系人沟通任何偏差

C.使用普遍接受的管理获得财务、法律和行政结尾

D.立即转到新项目的工作

PMP答案解析:项目已完成,下一步是按照流程进行项目收尾。选项A只是收尾的其中一个步骤,C更全面。

PMP参考答案:C

PMP考试试题二:

If a project has a 60 percent chance of a U.S. $100,000 profit and a 40 percent chance $100,000 loss, the expected monetary value for the project is: of a U.S.

A. $100,000 profit

B. $60,000 loss

C. $20,000 profit

D. $40,000 loss

假设有一项目,其获利100,000美元的概率为60%,损失100,000美元的概率为40%,那么该项目的预期货币价值为:

A. 获利100,000美元

B. 损失60,000美元

C. 获利20,000美元

D. 损失40,000美元

PMP答案解析:定量风险分析工具-建模和模拟-EMV(11.4.2.2) P338

PMP参考答案:C

阅读本文的人还阅读了:
北京PMP考试地点
上海PMP考试地点
深圳PMP考试地点
PMP认证考试的报名条件?
什么是PMP认证?
pmp是什么?
PMP认证考试费用(最新)

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库