PMP考试每天一练--PMP考试试题192
PMP考试试题一: All project deliverables are completed according to the customer’s expectations. The project manager is assigned to a new project with aggressive timelines.What should the project manager do next? A.archive all project documentation B.complete a financial analysis of the project and communicate any variance to stakeholders C.obtain financial, legal, and administrative closure using generally accepted practices D.move onto the new project immediately 所有项目可交付成果均已按照客户期望完成。项目经理被分配管理一个工期紧的新项目。项目经理接下来应该怎么做? A.将所有项目文档存档 B.完成项目的财务分析,并与干系人沟通任何偏差 C.使用普遍接受的管理获得财务、法律和行政结尾 D.立即转到新项目的工作 PMP答案解析:项目已完成,下一步是按照流程进行项目收尾。选项A只是收尾的其中一个步骤,C更全面。 PMP参考答案:C PMP考试试题二: If a project has a 60 percent chance of a U.S. $100,000 profit and a 40 percent chance $100,000 loss, the expected monetary value for the project is: of a U.S. A. $100,000 profit B. $60,000 loss C. $20,000 profit D. $40,000 loss 假设有一项目,其获利100,000美元的概率为60%,损失100,000美元的概率为40%,那么该项目的预期货币价值为: A. 获利100,000美元 B. 损失60,000美元 C. 获利20,000美元 D. 损失40,000美元 PMP答案解析:定量风险分析工具-建模和模拟-EMV(11.4.2.2) P338 PMP参考答案:C |