PMP考试试题一:

Which group has the responsibility to provide the resource for the quality management?

A. Project team members

B. Human resources

C. Functional organization

D. Management

下列哪一个群体有责任提供成功质量管理所需的资源?

A. 项目团队成员

B. 人力资源部

C. 职能型组织

D. 管理层

PMP答案解析:项目发起人责任

PMP参考答案:D. 管理层

PMP考试试题二:

A project is seriously delayed. Earned value analysis shows that the project needs to be completed 10 percent faster than the work has been going. To get the project back on track, management wants to add 10 people to an activity currently assigned to one person. The project manager disagrees, noting that such an increase will not produce an increase in speed. This is an example of:

A.The law of diminishing returns.

B.Fast tracking.

C.Earned value.

D.Life cycle costing.

项目已经严重滞后。挣值分析的结果表明,项目的进度应该比当前快10%。为了让项目回到正规,管理层希望增加10个人,到原来只有一个工作的活动上来。项目经理并不同意,因为他认为这种安排不一定会导致项目进度的加快。项目经理所说的是:

A. 边际效用递减原理

B.快速跟进

C.挣值

D.生命周期成本

审题:此题解题的关键是找到题干关键句“项目已经严重滞后”、 “一个工作的活动”

定位:项目时间管理的拓展。

解析:挣值管理EVM,注意EVM是绩效测量方法。

PMP参考答案:A. 边际效用递减原理

阅读本文的人还阅读了:
PMP培训证明是什么?
什么是PMP培训机构?
2017年PMP考试时间?
PMP退考需要什么条件?
上海PMP考试地点
深圳PMP考试地点

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库