PMP考试每天一练--PMP考试试题178
PMP考试试题一:
What function does the staffing management plan serve? A. It describes project roles and responsibilities. B. It is an organization chart that shows which organizational units are responsible for which work packages. C. It describes when and how human resources will be brought and taken off of the project team. D. It contains written outlines by job title of the competencies,responsibilities, and authority of a given job. 人员配备管理计划有什么功能? A.它描述项目角色和责任。 B.它是一份组织图,表明哪个组织单位负责哪个工作细目 C. 它描述人力资源何时、如何加入和退出项目团队。 D.它包括有给定工作的资格、职责、权限的工作名称构成的书面大纲。 PMP答案解析:人员配备管理计划 (9.1.3.1) P265 PMP参考答案:C.它描述人力资源何时、如何加入和退出项目团队 PMP考试试题二: You are working with a group of managers to decide which projects to pursue. Cost is an important consideration.Whick type of costs should not be a criteria in project selection? A.Indirect costs. B.Sunk costs. C.Tangible costs. D.Intangible costs. 你和一个经理团队一起决定进行哪一些项目,成本是重要的考虑因素,下面哪一项不是项目选择的标准? A.直接成本。 B.沉没成本。 C.有形成本。 D.无形成本。 审题:此题解题的关键是找到题干关键句“决定进行”、 “不是” 定位:成本管理的拓展。 PMP参考答案:B.沉没成本 |