PMP考试每天一练--PMP考试试题170
PMP考试试题一: A project manager plans to procure services from a vendor. The scope of services is clearly defined. However, the project manager expects there will be minor changes in the scope at a later stage. The project manager should use which of the following contract types? A. Fixed-price B. Time and material C. Cost-plus-incentive-fee D. Cost-plus-award-fee 项目经理打算向供货商采购服务。服务范围具有清晰定义。但是,项目经理希望在后续阶段服务范围的变更较小。项目经理应该采用下列哪一项合同类型? A.固定总价合同 B.工料合同 C.成本加激励酬金合同 D.成本加奖励费合同 PMP答案解析:规划采购输入:合同类型(12.1.1.9) P362 PMP参考答案:A.固定总价合同 PMP考试试题二: A project manager needs to analyze the project costs to find ways to decrease costs.it would be BEST if the project manager looks at: A.Variable costs and fixes costs. B.Fixed costs and indirect costs. C.Direct costs and variable costs. D.Indirect costs and direct costs. 项目经理需要分析项目成本,以找到降低成本的方法。他应该考虑以下哪项成本? A.可变成本和固定成本。 B.固定成本和间接成本。 C.直接成本和可变成本。 D.间接成本和直接成本。 审题:此题解题的关键是找到题干关键句“项目经理”“分析项目成本”和“降低成本”。 定位:成本管理领域的拓展 解析:直接成本和可变成本是直接归属于项目或随工作量而改变的成本,找到降低这些成本的方法才能有效地降低项目成本。 间接成本是无法直接追溯至某个具体项目的成本,因此只能按某种规定的会计程序进行累计并合理分摊到多个项目中,无法由项目经理控制降低,答案B和D排除。 . 固定成本不随项目变化而变化,也是无法直接追溯至某个具体项目的成本,答案A排除 PMP参考答案:C.直接成本和可变成本 |