PMP考试试题一:

Once signed, a contract is legally binding unless:

A. one party is unable to perform.

B. one party is unable to finance its part of the work.

C. it is in violation of applicable law.

D. it is declared null and void by either party's legal counsel.

合同一旦签订,就有法律效力,除非:

A. 一方不能履行。

B. 一方不能为其工作融资。

C. 它违反了法律。

D. 任何一方的法律顾问宣告其无效

PMP答案解析:合同无效情形

PMP参考答案:C. 它违反了法律。

PMP考试试题二:

If the rework became inevitable due to the lack of employee training and proper production controls, how much of this cost is directly attributable to the employees on the production line?

A.Approximately 15%.

B.Approximately 50%.

C.None.

D.100%.

如果因为缺少员工培训和恰当的生产控制而必须返工,那么多少返工成本可以直接归因于生产线的员工?

A.大约15%

B.大约50%

C.没有

D. 100%

审题:此题解题的关键是找到题干关键句“直接归因于”和“员工”。

定位:质量管理领域的拓展

解析:产品质量问题产生的成本大约85%由领导层负责,大约15%由员工负责。

PMP参考答案:A.大约15%

阅读本文的人还阅读了:
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库
PMP退考需要什么条件?
PMP退考费多少?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库