PMP考试每天一练--PMP考试试题161
PMP考试试题一: From the project perspective, quality attributes: A. determine how effectively the performing B. provide the basis for judging the project's success or failure. C. are specific characteristics for which a product is designed and tested. D. are objective criteria that must be met. 从项目的角度来看,质量特征: A. 决定了执行机构是否有效的支持项目 B. 提供了评判项目是否成功的基础 C. 是设计和测试产品的具体 D. 是必须满足的客观条件 PMP答案解析:质量管理引言 P228 PMP参考答案:C. 是设计和测试产品的具体特征 PMP考试试题二: It is crucial that your project team finish your project on time. Your team is using a technique to account for limited resources. You have also added a project buffer before the end date and feeding buffers before each critical task. What technique are you using? A. critical path analysis. B. PERT. C. critical chain. D. earned value. 你的项目团队必须按时完成项目。你的团队使用了一种考虑有限资源的技术,在最终日期前添加了缓冲并在关键活动上加入缓冲。这种技术叫做: A. 关键路径分析 B. 项目计划评审技术 C. 关键链 D. 挣值 审题:此题的关键字为“按时完成项目…一种考虑有限资源的技术,再最终日期前添加了缓冲并在 关键活动上加入缓冲”。讲的是制定进度计划的技术问题。考的是纯概念问题。 定位:规划过程组·项目时间管理·制定进度计划 解析: 1、关键链法是一种根据有限的资源来调整项目进度计划的进度网络分析技术; 2、资源约束型关键路径就是关键链。关键链法在网络图中增加作为“非工作进度活动”的持续时间缓冲,用来确定不确定性。 PMP参考答案:C. 关键链 |