PMP考试每天一练--PMP考试试题149

转载者:PMP团购网      发布时间:2017/9/15        点击: 2107

PMP考试试题一:

To use statistical quality Control effectively, the project team should know the differences between

A. Prevention and quality control

B. Attribute sampling and variables sampling

C. Attribute sampling and statistical sampling

D. Control limits and operational definitions

要有效地使用统计学进行质量控制,项目团队应该分清以下哪两个部分的区别?

A. 预防与质量控制

B. 属性抽样与变量抽样

C. 属性抽样与统计抽样

D. 控制限制和这个限制的操作定义

PMP答案解析:控制质量引言 (8.3) P248

PMP参考答案:B. 属性抽样与变量抽样

PMP考试试题二:

A project team is in the design stage of a new mountain bicycle prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost. Which of the following is the MOST likely technique used to determine these variables:

A. Benefit cost analysis.

B. Ishikawa diagram.

C. Design of experiments.

D. System flowchart.

团队成员正在处于一款新型山地自行车模型的设计阶段,他们正在确定使用何种类型的框架和材质能够在较低成本的前提下提供较高的绩效。他们正在使用以下哪项技术:

A.成本收益分析。

B.石川图。

C.实验设计。

D.系统流程图。

审题: 此题的关键字为“产品模型的设计阶段”、“较低的成本前提下”、“提供较高的绩效”“采用哪项技术”,题目属于质量管理知识领域,规划质量过程组,考察的知识点是工具与技术。

定位: 规划过程组·质量管理·规划质量

解析:

1、题目考察队质量管理知识领域工具和技术的理解;

2、题干没有提及成本及收益,排除选项A。 仔细阅读“正在确定使用何种类型的框架和材质能够…”这句话就可以排除选项A的干扰;选项B不是规划质量的工具(题干中未表明需要进行根本原因分析),排除;题干没有提及生产过程或者项目过程步骤间的相互关系,排除选项D;本题答案C;题干描述识别哪些因素会为正在生产产品的成本和绩效产生影响;

3、此题的场景描述正在从事活动所处的阶段,可以定位题目知识点范围。

PMP参考答案:C.实验设计。

阅读本文的人还阅读了:
PMP考试题库
PMP一般的学习流程简介
PMP项目管理考试费用变更
PMP考试难吗?
PMP考试成绩有几个M算通过?
深圳PMP培训哪个好?几大热门深圳PMP培训机构对比
PMP考试时间及PMP报名流程
PMP认证有什么价值?含金量如何?
PMP认证考试为什么需要报班?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库