PMP考试每天一练--PMP考试试题142

转载者:PMP团购网      发布时间:2017/9/1        点击: 2702

PMP考试试题一:

The project manager reviews the project chanter with the stakeholders. What is the step of the process?

A. Gain project charter approval

B. Develop the work breakdown structure

C. Form the project term

D. Develop the preliminary scope statement

项目经理在与项目干系人一起评审项目章程。该过程的下一步是什么?

A. 获得项目章程批准

B. 制定工作分解结构

C. 组建项目团队

D. 制定项目初级说明书

PMP答案解析:制定项目章程引言(4.2) P67

PMP参考答案:A. 获得项目章程批准

PMP考试试题二:

During project executing a project team member informs the project manager that based on her observations, the project cannot meet the quality standards set for it. The project manager meets with all parties concerned to analyze the situation. Which part of the quality management process is the project manager involved in:

A. Perform Quality Assurance.

B. Quality analysis.

C. Quality Control.

D. Plan Quality Management.

项目执行过程中,一团队成员告诉项目经理,根据她的研究,项目不能满足所设定的质量标准。于是项目经理和相关各方开会分析当前情况。项目经理正处于质量管理的哪个过程:

A.实施质量保证。

B.质量分析。

C.控制质量。

D.规划质量管理。

审题:此题的关键字为“执行过程”“项目不能满足质量标准”,题目属于质量管理知识领域。

定位:执行过程组·项目质量管理·实施质量保证

解析:

1、题干描述质量标准已经设定,排除选项D;选项B为干扰项,排除;(选项C是确认可交付成果,与题干描述不符,排除;选项A为确保项目符合质量标准,本地答案为A;)

2、区分实施质量保证和实施质量控制可以从两个过程的输出结果和所处的过程组记忆;

3、(此题的场景需要抽取关键信息来区分不同选项。) 根据题意,是项目执行过程中,发现项目不能满足质量指标,然后进行分析;是在实施质量保证。

PMP参考答案:A.实施质量保证。

阅读本文的人还阅读了:
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库
PMP一般的学习流程简介
PMP项目管理考试费用变更

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库