PMP考试每天一练--PMP考试试题139
PMP考试试题一: In some cases, contract termination refers to A. Contract closeout by mutual agreement B. Contract closeout by delivery of goods or services C. Contract closeout by successful performance D. Certification of receipt of final payment 在某些情况下,合同终止指: A. 双方同意终止合同 B. 交付产品或者提供服务结束合同 C. 正确履行合同从而结束合同 D. 确认最终付款 PMP答案解析:结束采购引言(12.4)P387 PMP参考答案:A. 双方同意终止合同 PMP考试试题二: You are contracting services for your current project. You need three chemical engineers to work on your project and you'll need specialized equipment and supplies to execute the project. The vendor has agreed to set the rates for the engineers at $275 per hour. The specialized equipment and supplies will be charged back to your organization as they're needed and purchased for the project. What type of contract is this: A. Fixed price B. Time and materials C. Cost-reimbursable D. Cost-reimbursable plus incentive 你需要对你当前项目中的某些服务外包,你需要三个化学工程师为你的项目工作,你还需要专业设备和供应品来执行项目。供应商同意按照每小时275美元收取工程师的费用,专业设备和供应品因为是你的项目所需要的采购,将计入你的公司账目来收款。这是什么合同类型: A. 固定总价合同。 B. 工料合同。 C. 成本补偿合同。 D. 成本加激励费用合同。 审题:此题的关键字为“合同类型”“每小时…的费用”,考察对不同类型合同概念的理解。 定位:规划过程组·项目采购管理·规划采购 解析:合同定价为小时费率,是工料合同的特征,本题答案为B; PMP参考答案:B. 工料合同。 |