PMP考试每天一练--PMP考试试题135
PMP考试试题一: Who is responsible for reporting the risk response plan, any unanticipated effects, and any corrections during the Monitor and Control Risks Process? A. Risk manager B. Project manager C. Project team D. Risk response responsible person 谁应该在控制风险过程中报告风险响应计划的有效性,任何预期之外的响应及任何纠正措施? A. 风险经理 B. 项目经理 C. 项目团队 D. 风险响应负责人 PMP参考答案:D. 风险响应负责人 PMP答案解析:规划风险应对(11.5) P343 PMP考试试题二: If a project manager focuses on ensuring that the project satisfies the needs for which it was undertaken, the project manager is involved in: A. Cost management. B. Time management. C. Quality management. D. Scope management. 如果项目经理一直关注确保项目满足需求,项目经理正处于: A.成本管理。 B.时间管理。 C.质量管理。 D.范围管理。 审题:此题的关键是“确保项目满足需求”。 定位:项目质量管理·前言 解析:提干中提到“符合需求”,当然和质量有关。 PMP参考答案:C.质量管理。 |