PMP考试每天一练--PMP考试试题133
PMP考试试题一: The seller tells you that your activities have resulted in an increase in their costs. You should: A. recommend a change to the project costs. B. have a meeting with management to find out what to do. C. ask the seller for supporting information. D. deny any wrongdoing. 卖方告诉你,你的经营活动使得卖方的成本增加了。你应该: A. 建议变更项目成本 B. 会见管理层,找到解决办法 C. 寻求卖方提供支持信息 D. 拒绝承认做错事 PMP参考答案:C. 寻求卖方提供支持信息 PMP答案解析:采购/成本问题 PMP考试试题二: Senior management asks the project manager how the project would be affected if two resources were removed from the project. To calculate a response, the project manager should complete: A. Resource leveling. B. What-if scenario analysis. C. Schedule compression. D. Fast tracking. 高级管理层询问项目经理,如果从项目中抽调两项资源是否会对项目造成影响。项目经理应该完成以下哪项来回答管理层的问题: A.资源平衡。 B.假设情景分析。 C.进度压缩。 D.快速跟进。 审题: 此题的关键是“从项目中抽调两项资源”。 定位: 规划过程组·项目时间管理·制定进度计划·假设情景分析 解析: 此题考的是假设情景分析的概念。 PMP参考答案:B.假设情景分析。 |