PMP考试试题一:

You manage a project whose team members have diverse skills and expertise. You want to encourage your staff to pool its knowledge about project issues to make the best decisions possible. The most appropriate management style to use is

A. Laissez-faire

B. Democratic

C. Autocratic

D. Directive

你负责管理一个项目,项目团队中成员拥有各种技能和特长。你想要劝说各位成员共享他们关于此项目的相关知识,以便做出更好的决策。最适合该过程的管理风格是:

A. 自由放任型

B. 民主型

C. 专制独裁型

D. 指导型

PMP参考答案:B. 民主型

PMP答案解析:人力资源管理-领导风格理论

PMP考试试题二:

You are given a new project to manage and a brief project scope statement. The project sponsor tells you that there is no required completion date for the project. The BEST thing to do is to:

A. Ask for better definition of the project scope before accepting the project.

B. Accomplish the project as time allows.

C. Plan the project as you would a normal project, but build in schedule flexibility.

D. Make a list of activities that need to be done.

分配给你了一个新项目,并且制定了简单的项目范围说明书。发起人告诉你,没有给项目规定具体的完工日期。此时,你最应该做的事情是什么?

A.在接受项目之前要求一份定义更详细的范围说明书。

B.顺其自然地实施项目。

C.像其它普通项目一样给项目进行规划,但进度的制定可以灵活些。

D.罗列一个需要完成工作的清单。

审题: 此题的关键是“新项目、没有给项目规定具体的完工日期、最应该做什么”

定位: 规划过程组·整合管理·制定项目管理计划

解析:

1、尽管项目没有规定完成日期,但也要对项目进行规划。因为没有硬性时间限制,所以进度计划可以根据资源的获得情况制定的灵活些,选项C正确;

2、一份简单的范围说明书并一定会对项目产生影响,所以选项A不正确;

3、尽管项目没有硬性的完工日期规定,但项目经理也不能不进行任何规划就随意地实施项目,所以选项B不正确;

4、选项D是制订进度计划的工作。

PMP参考答案:C.像其它普通项目一样给项目进行规划,但进度的制定可以灵活些。

阅读本文的人还阅读了:
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP考试内容和PMP考试题型
PMP认证在国内的含金量
PMP考试成绩大秘密

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库