PMP考试每天一练--PMP考试试题120

转载者:PMP团购网      发布时间:2017/7/12        点击: 2399

PMP考试试题一:

What is the main objective of the Executing Process group?

A. Tracking and reviewing the progress of the project

B. Managing stakeholder expectations

C. Satisfying the project specifications

D. Monitoring the schedule

执行过程组的主要目标是什么?

A. 跟踪并审查项目进度

B. 管理利害关系者的期望

C. 满足项目规范

D. 监控进度表

PMP参考答案:C. 满足项目规范

PMP答案解析:项目整合管理--执行过程组引言(4.3)P80

PMP考试试题二:

During a routine walkthrough, you discover that a seller has neglected to properly produce a major component of a deliverable. The seller tells you that the component is not included in the contract. What should you do FIRST?

A. Insist that the seller follow his quality assurance plans.

B. Send a letter to the seller insisting that the contract be adhered to.

C. Determine if the seller is correct, and whether the component could be reasonably considered part of the contract.

D. Inform the project sponsor of the discrepancy.

在例行检查中,你发现一卖方漏做了某一可交付成果中一个关键零件。卖方告诉你说合同中不包括这个零件。你首先应该怎么做?

A. 坚持卖方遵循他的质量保证计划。

B. 给卖方发封信件,要求他们遵守合同。

C. 确定卖方的说法是否正确。

D. 将此事告诉给项目发起人。

审题: 此题的关键字为“卖方说合同中不包括这个零件”,所以首先要明确这个说法是不是准确,才能确定下一步怎么做。

定位: 监控过程组·控制采购·检查和审计

解析:

1、虽然采购管理员可以是项目团队成员,但他通常向另一部门的经理报告。题干中说卖方告诉你说合同中不包括你经检查发现的卖方漏做的某一可交付成果中一个关键零件,所以你首先要对采购进行检查和审计,确定卖方说法是否正确,因此选项C为正确选项;

2、选项A是质量管理的内容,与题干要求无直接关系,所以不对;

3、选项B是在检查和审计后才酌情考虑需采取的措施,而不应该首先去做,因此选项B不正确;

4、在真实情况弄清楚前,不应告诉项目发起人,因此选项D也不对。

PMP参考答案:C. 确定卖方的说法是否正确。

阅读本文的人还阅读了:
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
PMP英文报名注意事项
PMP考试内容和PMP考试题型
PMP认证在国内的含金量
PMP考试成绩大秘密
PMP报考条件和PMP报考流程

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库