以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练--PMP考试试题113

转载者:PMP团购网      发布时间:2017/6/28        点击: 2730

PMP考试试题一:

Buyers use a variety of methods to provide incentives to a seller to complete work early or within certain contractually specified time frames. One such incentive is the use of liquidated damages. From the seller’s perspective, liquidated damages are what form of incentive?

A. Positive

B. Negative

C. Nominal

D. Risk-prone

买方利用许多方法激励卖方尽早完成或者按照合同规定的时间表完成项目工作。其中一个方法是清偿损失额。从卖方的角度看,清偿损失额是什么形式的激励:

A. 积极

B. 消极

C. 名义上的

D. 造成风险的

PMP参考答案:B. 消极

PMP答案解析:激励方式

PMP考试试题二:

The testing results for a new computer modulation project indicate a problem with the onboard computer’s sensors. The project manager calls a meeting with the team to analyze the problem. The project manager is involved in:

A. Quality management.

B. Perform Quality Assurance.

C. Plan Quality Management

D. Quality Control.

一款新型计算机调制解调器的测试结果表明,便携的计算机传感器出了问题。项目经理召集团队成员开会讨论。项目经理正在实施:

A.质量管理。

B.实施质量保证。

C.规划质量管理。

D.控制质量。

审题: 此题的关键字为“测试结果表明”,意思就是问题已经发生,目前是在质量控制过程。

定位: 监控过程组·质量管理·8.3 实施质量控制

解析:

1、题干描述说明问题已经发生,所以是实施质量控制的过程(选项D)。

2、质量管理由规划质量、质量保证和质量控制这三个过程组成,它本身并不是一个过程组,所以A选项不正确;

3、选项B是项目经理做完目前工作后下一步要做的;

4、题干描述说问题已经发生,所以C选项不对。

PMP参考答案:D.控制质量。

阅读本文的人还阅读了:
2017年PMP考试时间安排
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库