PMP考试每天一练--PMP考试试题110

转载者:PMP团购网      发布时间:2017/6/21        点击: 2442

PMP考试试题一:

Activity A has duration of 3 days and begins on the morning of Monday the 4th. The successor activity, B, has a finish-to-start relationship with A. The finish-to-start relationship has 3 days of lag, and activity B has duration of 4 days, Sunday is a non-workday.What can be determined from these data?

A. The total duration of both activities is 8 days.

B. Calendar time between the start of A to the finish of B is 11 days.

C. The finish date of B is Wednesday the 13th.D. Calendar time between the start of A to the finish of B is 14days.

活动A的持续期3天,而且要在星期一(4号)开始。接下来的活动B和活动A是首尾相连的关系。这种首尾相连的关系中间又发生了3天的滞后时间,而且活动B的持续时间是4天。星期日是公休日。根据这些数据你能得出下列哪个结论?

A. 两项活动的总持续期为8天

B. 从A开始到B结束的日历天数为11天

C. B活动结束的日期是星期三(13号)

D. 从A开始到B结束的日历天数为14天

PMP参考答案:B. 从A开始到B结束的日历天数为11天

PMP答案解析:制定进度计划

PMP考试试题二:

The requirements of many stakeholders were not approved for inclusion in your project. Therefore, you had a difficult time receiving formal approval of the project management plan for this project. The stakeholders argued and held up the project while they held meeting after meeting about their requirements. The project was finally approved and work was began six months ago. All of the following would be good preventive actions to implement EXCEPT:

A. Keep a file of what requirements were not included in the project.

B. Make sure the change control process is not used as a vehicle to add back the requirements into the project.

C. Maintain an issue log.

D. Hold meetings with the stakeholders to go over the work that will not be added to the project.

项目上很多干系人的需求没有得到批准,所以项目管理计划在得到正式批准上遇到了很大的困难。在他们的需求没有满足之前,他们开会争论并阻止项目开始。最终在六个月前,项目得到了正式批准并开始实施。在执行过程中以下均是有效的预防措施,除了:

A. 将没有包含在项目中的需求记录在案。

B. 确保变更控制流程没有阻碍干系人的需求被增加到项目上。

C. 保留问题日志。

D. 和干系人开会讨论将不会增加到项目上的工作。

审题: 项目管理计划难产,虽最终得以批准实施但其中难免潜含着诸多有碍执行的隐患。

定位: 执行过程组·项目干系人管理·管理干系人参与

解析: 1. 问题日志或行动日志可用来记录和监督问题的解决情况。它可以促进沟通,确保对问题有统一认识。因此选项A和选项C利于预防问题发生; 2. 选项B是有效的干系人期望管理举措; 3. 选项D只能是问题更加复杂化,因此选项D符合题干要求。

PMP参考答案:D. 和干系人开会讨论将不会增加到项目上的工作。

阅读本文的人还阅读了:
2017年PMP考试时间安排
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP考试内容和PMP考试题型
PMP认证在国内的含金量
PMP考试成绩大秘密
PMP报考条件和PMP报考流程

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库